Squeeze Play: Inserting the Final Deck Sections
Previous posts in the New Narrows Bridge Series:

As bridge sections continue to be added, either by direct lift or trapeze, the moment of truth must arrive: placing the final sections into position. With all sections in place save the last four, the remaining spaces are only 8 mm. wider than the sections which will bridge them.
The gaps which will hold the final sections lie on either side of the towers. The sections lying between the tower legs are the shortest, and will be moved first to place the 3rd and 4th sections, connecting the short tower segments with center span.


The last two sections, on the shore-side of the towers, are a bit more challenging. The long sections between the anchors and the towers are far more massive than the tower sections, and require a different approach. Nine sections are joined — nearly a quarter-mile in length — between the anchors and the gap on the outside of the towers. Engineers fasten metal rods to the last section closest to the anchor, passing them through the concrete of the anchors, behind which are placed hydraulic jacks. These jacks provide the 414,000 pounds of force required to pull the joined sections toward the anchors, increasing the gap sufficiently to place the last section.
This move is possible because the final piece joining these sections to the anchors — a large expansion joint — has not yet been placed.
